Sewage Treatment Plant in Bad Oeynhausen, Germany

2937

Project Overview

  • Sewage treatment plant of the city of Bad Oeynhausen
  • Capacity: 78,500 PT
  • Current working load: 68.500 PT
  • Sewage treated per year: 6.500.000 m³/a
  • Volume of sludge activation 15.500 m³
  • Dry weather discharge 11.000 m³/d
  • Storm water flow 58.800 m³/d
  • Construction Period: 1991 – 1994
  • Contract Price: 20,000,000 €